| BAI Number: | 21202.00.01 |
| Bid Schedule: | Unit Price Bid Schedule |
| Probable Construction Cost: | $150,000.00 to $170,000.00 |
|
Deposit for Plans & Specs: (Includes sales tax) |
$31.80 (Half-size) - Non-refundable $21.20 (Electronic) - Non-refundable |
| Project Bid Date: | 08/02/2010 |
| Project Bid Time: | 07:00 PM |
| Project Bid Location: | City of Lake Norden, PO Box 213, 508 Main Avenue, Lake Norden, SD 57248-0213 |
| Project Deadlines: |
11/12/2010 for substantial completion 11/26/2010 for final completion |
| Addendum Dates: |
07/28/2010 Faxed
- Click here to download
|
Scope of Work:
|
|