Arlington Birch Street Utilities and Reconstruction
BAI Number: 08009.00.08
Bid Schedule: Unit Price Bid Schedule
Probable Construction Cost: $300,000.00 to $350,000.00
Deposit for Plans & Specs:
(Includes sales tax)
$31.80 (Half-size) - Non-refundable
$21.20 (Electronic) - Non-refundable
 
Project Bid Date: 09/02/2009
Project Bid Time: 11:00 AM
Project Bid Location: City of Arlington, 202 West Elm Street, Arlington, SD 57212
Project Deadlines: 07/31/2010 for substantial completion
08/28/2010 for final completion
 
Addendum Dates: 08/31/2009 Faxed - Click here to download
09/01/2009 Faxed - Click here to download

Scope of Work:
  • Install approximately 715 LF of 8-inch PVC gravity sewer pipe
  • Install approximately 3 sanitary sewer manholes and 13 sewer services
  • Install approximately 885 LF of 8-inch and 6-inch PVC water main pipe
  • Install approximately 13 water service connections along with associated water main valves and fittings
  • Place approximately 3,000 ton of gravel base course with dust control agent
  • Place approximately 1,540 LF of concrete curb and gutter, and
  • Install 2 storm sewer junction boxes with associated storm sewer pipe.
Contact Persons:
  • Civil- Scott Mohror, Banner Associates, Inc. (605) 692-6342