Worthington Public Utilities Well #30 Replacement
BAI Number: 20785.00.00
Bid Schedule 1: Unit Price Bid Schedule
Bid Schedule 2: Unit Price Bid Schedule
Probable Construction Cost 1: $68,280.00
Probable Construction Cost 2: $65,290.00
Deposit for Plans & Specs:
(Includes sales tax)
$32.00 (Half-size) - Non-refundable
$21.00 (Electronic) - Non-refundable
 
Project Bid Date: 07/24/2008
Project Bid Time: 02:00 PM
Project Bid Location: Worthington Public Utilities Board Room
Project Deadlines 1: 12/01/2008 for substantial completion
12/31/2008 for final completion
Project Deadlines 2: 12/01/2008 for substantial completion
12/31/2008 for final completion
 
Addendum Dates: 07/08/2008 Mailed - Click here to download

Scope of Work 1:
  • Construction of Well #30 Replacement using PVC casing.
Scope of Work 2:
  • Construction of Well #30 Replacement using steel casing.
Contact Persons:
  • Dennis Odens, Banner Associates, Inc. - St. Peter location (507) 931-0930